← University
Defences: How Defendants Respond and What They Can Raise
0 of 4

A statement of claim arrived by registered mail at a general contractor's office in Edmonton, its blue backing and formal typeface announcing litigation that would consume the company for months to come. The plaintiff was a non-profit community services agency that had retained the contractor more than 4 years earlier to renovate an aging facility used to deliver programming for vulnerable populations. The pleading alleged serious structural deficiencies and water infiltration problems, claimed breach of contract and negligence, and sought damages running into hundreds of thousands of dollars for remediation costs and disruption to operations.

The renovation project had presented challenges from the outset. The building was old, and during construction the contractor had raised concerns about drainage issues that predated his involvement. Foundation work and waterproofing had been performed by a subcontractor whose methods the general contractor had questioned at the time, though the project had ultimately proceeded to completion and a final inspection certificate had been issued in the spring of the year following substantial performance. In the months after completion, the contractor recalled receiving some communications about minor concerns, but those exchanges had tapered off and he had heard nothing of substance from the agency for a considerable period before the claim arrived.

The timeline embedded in the statement of claim prompted immediate questions. The renovation had been completed more than 4 years before the action was commenced, and the contractor could not recall any significant complaints during the intervening period that might have preserved the agency's right to sue. The subcontractor whose foundation work lay at the heart of the alleged deficiencies had also been named in the proceeding, raising questions about the allocation of responsibility among the parties and the availability of contribution and indemnity.

The litigation developed along multiple fronts. The agency pursued its claims against both the contractor and the subcontractor, while the contractor filed a Third Party Notice seeking contribution and indemnity from the subcontractor in the event liability was established. The subcontractor's exposure to the agency's direct claim was eventually resolved when those proceedings were dismissed as limitation-barred, and the agency subsequently delivered a Notice of Discontinuance formally ending its remaining proceedings against the subcontractor in the main action. That discontinuance, however, left unresolved the contractor's third-party claim against the subcontractor, creating a procedural situation in which the subcontractor was no longer a defendant to the agency's action but remained potentially liable to the contractor for contribution and indemnity.

Affirmative Defences: Raising Something Beyond a Denial

The general contractor's office sits quiet on a Thursday evening, the day's crew long since dispersed to their homes across the city. At the drafting table, surrounded by rolled blueprints and specification binders from projects spanning two decades, the contractor reviews the legal documents delivered that afternoon by registered mail. The statement of claim names his company as the defendant in an action brought by a non-profit community services agency, alleging that renovation work completed years earlier has resulted in structural deficiencies, water infiltration, and consequential damages to programming operations. The claimed amount runs into hundreds of thousands of dollars. The contractor reads the allegations carefully, his memory reaching back to the project itself, to the challenges of working on an aging building, to the concerns he raised during construction about drainage issues that predated his involvement, to the subcontractor whose foundation work he had questioned at the time. He remembers, too, the conversations with the agency's representatives during the project, their eagerness to complete the renovation quickly to satisfy their government funder, their decisions to defer certain recommendations he had made. As he considers how to respond to this lawsuit, he realizes that his defence will need to go far beyond simply denying that deficiencies exist or that his work caused them. His response will need to raise matters that, even if the plaintiff proves some breach on his part, will shift responsibility, reduce his exposure, or potentially eliminate his liability altogether. This is the domain of affirmative defences, and understanding them is essential for any defendant facing civil litigation in Alberta.

When a plaintiff commences an action alleging that a defendant has caused harm through negligence, breach of contract, or some other actionable wrong, the defendant's first instinct is often to deny the allegations. A simple denial asserts that the plaintiff's version of events is incorrect, that the defendant did not do what is alleged, that no breach occurred, or that the plaintiff suffered no damages. Such denials place the burden on the plaintiff to prove its case, and if the plaintiff fails to meet that burden, the defendant succeeds without having to establish anything independently. However, litigation rarely proceeds on such clean lines. In most cases, the factual record is mixed, with evidence supporting some of the plaintiff's contentions while contradicting others. More importantly, there are circumstances in which a defendant may acknowledge that something went wrong in a general sense while nonetheless asserting that legal responsibility should not rest entirely, or at all, with the defendant. This is where affirmative defences become critical. Unlike a denial, which simply puts the plaintiff to its proof, an affirmative defence raises new matter that, if established, provides a complete or partial answer to the plaintiff's claim even if the plaintiff proves the essential elements of its case. The defendant who raises an affirmative defence is not merely saying that the plaintiff is wrong but is instead saying that, even if the plaintiff is right about certain facts, there are other facts or legal principles that should alter the outcome.

The distinction between a denial and an affirmative defence carries significant procedural and strategic implications. Under the Alberta Rules of Court, a defendant must specifically plead any affirmative defence on which it intends to rely. The rules require that a statement of defence set out the material facts on which the defendant relies, and this includes the factual foundation for any affirmative defence. If a defendant fails to plead an affirmative defence, the court may refuse to allow the defendant to pursue that defence at trial, on the basis that the plaintiff has been deprived of fair notice and the opportunity to respond. This pleading requirement reflects a fundamental principle of civil litigation, namely that both parties are entitled to know the case they must meet. A plaintiff who believes it need only prove negligence and damages may be caught unprepared if the defendant springs an unpleaded defence at trial, and the rules guard against such unfairness. For the contractor facing the non-profit agency's claim, this means that the statement of defence must do more than simply deny the allegations of deficient work. If the contractor intends to argue that the agency's own conduct contributed to the damages, or that the agency failed to take reasonable steps to minimize its losses, or that the agency voluntarily accepted certain risks, these matters must be pleaded with sufficient particularity that the agency understands the nature of the defence and can prepare accordingly.

Among the most significant affirmative defences available in negligence actions in Alberta is contributory negligence. This defence acknowledges that the defendant may have been negligent in some respect but asserts that the plaintiff's own negligence also contributed to the loss suffered. The legal framework for contributory negligence in Alberta is established by the Contributory Negligence Act, which fundamentally altered the common law approach to situations where both parties bear some fault. Under the historical common law rule, a plaintiff whose own negligence contributed in any degree to the harm suffered was completely barred from recovery against a negligent defendant. This all-or-nothing approach produced harsh results, denying compensation to plaintiffs who might have been only marginally at fault while allowing defendants who were primarily responsible to escape liability entirely. The Contributory Negligence Act replaced this rule with a system of apportioned liability, under which damages are divided among the parties according to their respective degrees of fault. If both the plaintiff and the defendant are found negligent, and if each party's negligence contributed to the damages, the court apportions liability based on a percentage assessment of each party's responsibility. The plaintiff's recovery is then reduced by the percentage of fault attributed to the plaintiff's own conduct. This approach reflects a more nuanced understanding of causation and responsibility, recognizing that real-world situations often involve multiple contributing factors and that fairness is better served by apportioning loss than by adopting an absolute rule in either direction.

For the contractor in the renovation dispute, a contributory negligence defence might be grounded in several factual contentions. The contractor may argue that the agency's own conduct during and after the project contributed to the damages now claimed. Perhaps the agency failed to report problems when they first became apparent, allowing water infiltration that might have been easily remedied at an early stage to cause progressive structural damage over subsequent years. Perhaps the agency ignored or delayed acting on recommendations the contractor made during construction, choosing instead to save costs or accelerate the project timeline in ways that compromised the long-term integrity of the work. Perhaps the agency's own maintenance practices after the project was complete were inadequate, contributing to deterioration that would not have occurred had the building been properly cared for. Each of these scenarios, if supported by evidence, could form the basis of a contributory negligence defence. The contractor would need to establish both that the agency failed to exercise reasonable care in some respect and that this failure contributed to the damages claimed. If successful, this defence would not eliminate the contractor's liability but would reduce the damages payable in proportion to the agency's share of fault. If the court were to find the contractor sixty percent at fault and the agency forty percent at fault, the agency's recovery would be reduced by forty percent, reflecting its own contribution to the loss.

The burden of proof for contributory negligence rests with the defendant who raises it. Unlike a simple denial, which merely challenges the plaintiff to prove its case, an affirmative defence requires the defendant to establish the factual and legal elements on which the defence depends. The contractor cannot simply assert in general terms that the agency was also negligent. The contractor must prove, on a balance of probabilities, that the agency breached some duty of care owed to itself or to the contractor, that this breach fell below the standard of a reasonable person in the agency's circumstances, and that the breach was a contributing cause of the damages claimed. This requires evidence, and in a case where the agency's internal documentation is sparse, the contractor may need to rely on testimony, correspondence, site photographs, and expert opinion to reconstruct what the agency knew, when it knew it, and what a reasonable building owner would have done in response. The question of when the agency first became aware of problems, or when it should have become aware through reasonable inspection and oversight, becomes critical not only for limitation period purposes but also for assessing the agency's own conduct in responding to developing issues.

Closely related to contributory negligence, but conceptually distinct, is the defence of failure to mitigate. This defence arises from the common law principle that a plaintiff who has suffered loss at the hands of a defendant is obligated to take reasonable steps to minimize that loss. A plaintiff cannot sit passively while damages mount and then seek to recover the full extent of its accumulated losses from the defendant. The plaintiff must act reasonably to limit the harm, and if the plaintiff fails to do so, the defendant is not liable for that portion of the damages that the plaintiff could reasonably have avoided. The failure to mitigate defence differs from contributory negligence in a subtle but important way. Contributory negligence concerns the plaintiff's conduct that contributed to the initial wrong or the occurrence of the harm. Failure to mitigate concerns the plaintiff's conduct after the harm has occurred, in failing to take reasonable steps to limit its extent. A plaintiff might have been entirely without fault in the events leading up to the loss but may nonetheless have failed to mitigate by not acting reasonably afterward. Conversely, a plaintiff who was contributorily negligent in causing the loss might still have acted reasonably to mitigate it. The two defences can coexist in the same case, and a defendant may rely on both.

In the context of the construction deficiency claim, the contractor might argue that the agency failed to mitigate its damages by not addressing the emerging problems in a timely manner. If water infiltration began to appear within a year or two after the renovation, and if the agency observed this infiltration but took no steps to investigate its source or remedy its effects, the resulting structural damage over subsequent years might have been substantially reduced or avoided altogether by earlier intervention. The contractor might retain an expert to testify that, had the agency acted promptly when the first signs of water damage appeared, the total cost of remediation would have been a fraction of what is now claimed. The contractor would argue that the agency's inaction allowed a manageable problem to become a major one, and that the agency should not be permitted to recover the costs of damage that reasonable action on its part would have prevented. The burden of proof on failure to mitigate also rests with the defendant, who must establish both that the plaintiff failed to take reasonable steps and that such steps would have reduced the damages. The reasonableness inquiry is sensitive to the plaintiff's circumstances, including its financial resources, expertise, and access to information. A non-profit agency operating on limited funds and relying on volunteer board oversight might not be held to the same standard of vigilance as a sophisticated commercial property owner, and the contractor's defence must grapple with these contextual factors.

A third affirmative defence that may arise in certain circumstances is voluntary assumption of risk, known by the Latin phrase volenti non fit injuria. This defence holds that a plaintiff who voluntarily assumes a known risk cannot recover against a defendant for harm that results from that risk materializing. The defence is complete rather than partial. If established, it eliminates the defendant's liability entirely, rather than merely reducing it in proportion to fault. However, the requirements for this defence are stringent, and courts apply it narrowly. To succeed on a voluntary assumption of risk defence, the defendant must establish that the plaintiff had full knowledge of the specific risk that caused the harm, that the plaintiff understood and appreciated the nature and extent of that risk, and that the plaintiff voluntarily agreed to accept it. A general awareness of danger is not sufficient. The plaintiff must have known of the particular risk at issue and must have consented to bear the consequences of that risk. Furthermore, the plaintiff's consent must have been truly voluntary, not coerced by circumstances or by an inequality of bargaining power that left the plaintiff with no practical choice.

In the renovation context, a voluntary assumption of risk defence might be raised if the contractor can establish that the agency was advised of specific risks during the project and chose to proceed despite those warnings. If the contractor recommended a particular approach to foundation waterproofing, explained the risks of an alternative approach that the agency preferred for cost reasons, and the agency directed the contractor to proceed with the riskier method despite full knowledge of the potential consequences, the contractor might argue that the agency assumed the risk of the very deficiency now complained of. This defence would require clear evidence of the warning given, the agency's understanding of the risk, and the agency's decision to proceed nonetheless. It would likely require documentary evidence, such as contemporaneous correspondence, meeting minutes, or written acknowledgments, although witness testimony might also be relevant. The difficulty with this defence in many construction cases is that owners often rely on contractors for guidance and may not fully appreciate the technical implications of decisions they are asked to make. A court would scrutinize whether the agency, operated by a volunteer board and lacking construction expertise, truly had the knowledge and understanding necessary to constitute voluntary assumption of a technical risk. The defence is available in principle, but its success depends heavily on the specific facts.

It is important to distinguish between defences that reduce liability and defences that eliminate it entirely. Contributory negligence and failure to mitigate are both partial defences in the sense that, if established, they reduce the plaintiff's recovery without necessarily eliminating it. The plaintiff who is found to be contributorily negligent may still recover, but the recovery is reduced by the percentage of fault attributed to the plaintiff. The plaintiff who fails to mitigate may still recover the damages that were unavoidable, but not the damages that reasonable mitigation would have prevented. These defences operate by adjusting the quantum of damages rather than negating the defendant's liability in full. By contrast, voluntary assumption of risk, if established, is a complete defence that bars the plaintiff's recovery entirely. The same is true of other complete defences such as limitation periods, which cut off the plaintiff's right to sue regardless of the merits of the underlying claim. Understanding whether a defence is complete or partial is essential for both pleading and settlement purposes. A defendant who has a strong partial defence may be unable to defeat the claim entirely but may substantially reduce the exposure, making settlement more attractive to both parties. A defendant who has a potential complete defence faces a higher-risk, higher-reward situation, because success means no liability but failure means the defence provides no reduction in damages at all.

The interplay among multiple defences can produce complex outcomes at trial. The contractor facing the agency's claim might plead all three defences discussed here, along with additional defences not addressed in this lesson, such as limitation period arguments or assertions that a subcontractor bears primary responsibility. Each defence must be supported by its own factual foundation, and the evidence required for one defence may overlap with or contradict the evidence for another. For example, the contractor might argue both that the agency assumed the risk of water infiltration by choosing a particular construction method and that the agency was contributorily negligent in failing to maintain the building after construction. These defences are not necessarily inconsistent, but they rest on different factual premises and require different elements to be established. The contractor's legal counsel must carefully assess which defences are supportable on the evidence, which defences are consistent with each other, and how to present a coherent theory of the case that allows the trier of fact to understand why the contractor should not bear full responsibility for the claimed losses.

The evidence available to support affirmative defences in construction cases often depends heavily on contemporaneous documentation. Project files, daily logs, correspondence with the owner, meeting minutes, change orders, site inspection reports, and photographs all become critical when reconstructing events years after the fact. In the scenario presented, the agency did not document the project well at the time, which may hamper its ability to prove its own case. However, the same lack of documentation may also affect the contractor's ability to prove affirmative defences. If the contractor warned the agency about a particular risk but did not document that warning in writing, proving the warning years later becomes a matter of credibility and recollection. If the contractor observed the agency making decisions that contributed to the deficiencies but did not record those observations, establishing contributory negligence requires reliance on memory that may have faded or become unreliable. Good practice for any contractor, and indeed for any party to a business relationship, is to document significant communications and decisions in writing, not only to protect against future litigation but also to ensure clarity and alignment during the project itself. The lesson for defendants facing claims arising from past projects is that the quality of the defence may depend on the quality of the records that can be marshaled in support.

The presence of a government funder with its own interest in the outcome adds another dimension to the litigation. The funder contributed capital toward the renovation and may be concerned about the disposition of public funds if the project resulted in a deficient building. The funder may have rights under its funding agreement with the agency, including rights to information, audit, or participation in decisions about pursuing claims. From the contractor's perspective, the funder's involvement may be relevant to the defences raised. If the funder imposed conditions on the project that contributed to the deficiencies, such as timelines or budget constraints that affected construction decisions, the contractor might argue that responsibility should be shared more broadly. If the funder was aware of emerging problems and pressured the agency not to pursue remediation or not to raise concerns with the contractor, this might be relevant to failure to mitigate or other defences. The contractor's investigation of the facts should include inquiry into the funder's role and knowledge, because evidence of the funder's conduct may support the affirmative defences being raised.

The board of directors of the non-profit agency, weighing whether to pursue the claim against the contractor, should understand that the litigation will not be a one-sided affair in which the agency presents its evidence and the contractor simply denies everything. The contractor will raise affirmative defences, and those defences will put the agency's own conduct at issue. Board members and staff may be called as witnesses and examined about what the agency knew, when it knew it, what decisions were made, and why. The agency's records, such as they are, will be produced and scrutinized. The agency's expert may be cross-examined on whether the damages could have been reduced by earlier intervention. The litigation will become a forum in which the agency's own actions are evaluated, and the outcome will depend not only on what the contractor did wrong but also on what the agency did or failed to do. This is the nature of civil litigation when affirmative defences are in play. The defendant does not passively await judgment but actively shifts attention to the plaintiff's conduct, seeking to reallocate responsibility and reduce exposure.

For defendants in Alberta civil litigation, affirmative defences represent essential tools for achieving a just outcome in cases where responsibility is shared or where the plaintiff's own conduct has contributed to the loss. These defences must be pleaded specifically, proved with evidence, and argued coherently. They may reduce damages, as with contributory negligence and failure to mitigate, or they may eliminate liability entirely, as with voluntary assumption of risk.

Continue with University access

This lesson is part of a $79 course. Purchase the course or sign in with an active membership to keep reading.

See purchase options