← University
Defences: How Defendants Respond and What They Can Raise
0 of 4

A statement of claim arrived by registered mail at a general contractor's office in Edmonton, its blue backing and formal typeface announcing litigation that would consume the company for months to come. The plaintiff was a non-profit community services agency that had retained the contractor more than 4 years earlier to renovate an aging facility used to deliver programming for vulnerable populations. The pleading alleged serious structural deficiencies and water infiltration problems, claimed breach of contract and negligence, and sought damages running into hundreds of thousands of dollars for remediation costs and disruption to operations.

The renovation project had presented challenges from the outset. The building was old, and during construction the contractor had raised concerns about drainage issues that predated his involvement. Foundation work and waterproofing had been performed by a subcontractor whose methods the general contractor had questioned at the time, though the project had ultimately proceeded to completion and a final inspection certificate had been issued in the spring of the year following substantial performance. In the months after completion, the contractor recalled receiving some communications about minor concerns, but those exchanges had tapered off and he had heard nothing of substance from the agency for a considerable period before the claim arrived.

The timeline embedded in the statement of claim prompted immediate questions. The renovation had been completed more than 4 years before the action was commenced, and the contractor could not recall any significant complaints during the intervening period that might have preserved the agency's right to sue. The subcontractor whose foundation work lay at the heart of the alleged deficiencies had also been named in the proceeding, raising questions about the allocation of responsibility among the parties and the availability of contribution and indemnity.

The litigation developed along multiple fronts. The agency pursued its claims against both the contractor and the subcontractor, while the contractor filed a Third Party Notice seeking contribution and indemnity from the subcontractor in the event liability was established. The subcontractor's exposure to the agency's direct claim was eventually resolved when those proceedings were dismissed as limitation-barred, and the agency subsequently delivered a Notice of Discontinuance formally ending its remaining proceedings against the subcontractor in the main action. That discontinuance, however, left unresolved the contractor's third-party claim against the subcontractor, creating a procedural situation in which the subcontractor was no longer a defendant to the agency's action but remained potentially liable to the contractor for contribution and indemnity.

Limitation as a Complete Defence: The Shield That Ends the Claim

The letter arrived at the general contractor's office on a Tuesday morning in late October, delivered by registered mail with the return address of a downtown Edmonton law firm. Inside, the contractor found a statement of claim naming his company as the defendant in an action brought by the community services agency whose facility he had renovated years earlier. The claim alleged deficient workmanship, breach of contract, and negligence in connection with foundation work and waterproofing that had, according to the pleading, resulted in ongoing structural problems and water infiltration causing hundreds of thousands of dollars in damage. The contractor read through the allegations with a mix of frustration and disbelief, noting the dates referenced in the document and performing a quick mental calculation. He had completed that renovation project more than four years ago. The final inspection certificate had been issued in the spring of a year now receding into the past, and while he vaguely recalled some communications about minor concerns in the months following completion, he had heard nothing of substance from the agency for a very long time. His first call was to his lawyer, and his first question was whether he even had to respond to this claim at all given how much time had passed since the work was done.

That’s the free preview

You’ve reached the end of what’s open to read. The rest of this lesson is part of a $79 course — purchasing unlocks it, or sign in if you already have access.