← University
Builders Risk and Course of Construction Coverage
0 of 4

A development company based in Toronto undertook the construction of a 28-storey residential condominium tower on a site it had acquired 3 years earlier through an arm's-length transaction. The project budget exceeded $95 million, with financing provided by a consortium of 2 institutional lenders who required evidence of builders risk insurance naming them as loss payees before any draw on the construction loan could be advanced. The development company engaged a general contractor under a stipulated-price contract valued at approximately $72 million, with a scheduled completion date 26 months from the commencement of excavation work.

The construction contract allocated responsibility for procuring builders risk coverage to the development company, which obtained a policy through its insurance broker with limits corresponding to the completed value of the structure. The policy named the development company as the first named insured, with the general contractor, all subcontractors of every tier, and the lending consortium listed as additional insureds or loss payees according to their respective interests. Coverage was written on an all-risk basis subject to standard exclusions, with the policy period running from groundbreaking through to substantial completion or first occupancy, whichever occurred earlier.

By month 14 of construction, the tower had reached its full height and the exterior envelope was nearly complete when a fire broke out on the 19th floor during overnight hours. The fire caused significant damage to structural steel, mechanical rough-ins, and interior finishing work across 4 floors before firefighters brought it under control. The direct physical damage was estimated at $4.2 million, but the project schedule was disrupted by approximately 5 months while engineers assessed structural integrity, damaged work was demolished, and replacement materials were procured and installed.

The extended timeline triggered substantial additional costs beyond the physical repair. The development company continued to pay interest on drawn loan amounts during the delay, incurred ongoing insurance premiums for the uncompleted structure, and absorbed consultant fees for revised scheduling and engineering review. Marketing commitments made to prospective purchasers required adjustment, and the delay pushed occupancy of the first units past the date when rental income had been projected to begin offsetting carrying costs. The general contractor submitted claims for extended general conditions and acceleration costs, while several subcontractors asserted that the delay entitled them to additional compensation under their respective contracts.

The development company's insurance broker received notice of the loss and began working with the insurer's adjuster to determine the scope of coverage available under the builders risk policy for both the direct physical damage and the consequential financial losses that continued to accumulate as reconstruction proceeded.

Soft Costs and Delay in Opening Coverage: The Extensions That Matter on Large Projects

Construction projects operate within intricate timelines where every delay carries measurable financial consequences extending far beyond the immediate physical damage that caused the interruption. When a fire damages the structural steel on a partially completed condominium tower in Toronto, the direct property damage represents only a fraction of the total loss the developer will ultimately bear. The costs of extended financing, continued insurance premiums on the uncompleted structure, consultant fees during the extended construction period, and lost rental income from units that should have been occupied all compound rapidly. These consequential losses, broadly categorized as soft costs and delay in opening expenses, constitute some of the most significant exposures facing major construction projects across Canada, yet they remain among the most misunderstood elements of builders risk insurance programs.

The distinction between hard costs and soft costs in construction provides the essential framework for understanding why standard builders risk coverage, while critical, addresses only part of the financial exposure during a project. Hard costs represent the tangible expenses directly associated with physical construction, including materials, labour, equipment, and contractor fees for actual building work. Soft costs encompass the broader project expenses that do not directly produce physical construction but remain essential to project completion and delivery. These include architectural and engineering fees, legal costs, financing charges, permit fees, property taxes during construction, insurance premiums, marketing expenses for projects intended for sale, and the various administrative costs that continue whether or not hammers are swinging. Standard builders risk policies covering the hard costs of construction will respond to rebuild damaged property, but they typically exclude the cascade of consequential expenses that flow from construction delays unless specific soft cost coverage has been purchased.

That’s the free preview

You’ve reached the end of what’s open to read. The rest of this lesson is part of a $79 course — purchasing unlocks it, or sign in if you already have access.