Calendar·Insurance·Specialty Lines
Builders Risk and Course of Construction Coverage
FACULTY OF INSURANCESpecialty Lines • ~30 min

How builders risk and course of construction insurance works in Canada — what is covered during construction, how the policy interacts with other construction coverages, and how to manage the policy through the project lifecycle.

Builders Risk and Course of Construction Coverage

Price
$79
Lessons
4
Enroll
Share
EmailLinkedIn

What this course covers

01Builders Risk Coverage: Structure, Purpose, and Who Should Be Insured
02What Builders Risk Covers and What It Excludes: The Coverage Gap Reality
03Soft Costs and Delay in Opening Coverage: The Extensions That Matter on Large Projects
04Managing the Builders Risk Policy Through the Project: Key Decision Points

Scenario

A development company based in Toronto undertook the construction of a 28-storey residential condominium tower on a site it had acquired 3 years earlier through an arm's-length transaction. The project budget exceeded $95 million, with financing provided by a consortium of 2 institutional lenders who required evidence of builders risk insurance naming them as loss payees before any draw on the construction loan could be advanced. The development company engaged a general contractor under a stipulated-price contract valued at approximately $72 million, with a scheduled completion date 26 months from the commencement of excavation work.

The construction contract allocated responsibility for procuring builders risk coverage to the development company, which obtained a policy through its insurance broker with limits corresponding to the completed value of the structure. The policy named the development company as the first named insured, with the general contractor, all subcontractors of every tier, and the lending consortium listed as additional insureds or loss payees according to their respective interests. Coverage was written on an all-risk basis subject to standard exclusions, with the policy period running from groundbreaking through to substantial completion or first occupancy, whichever occurred earlier.

By month 14 of construction, the tower had reached its full height and the exterior envelope was nearly complete when a fire broke out on the 19th floor during overnight hours. The fire caused significant damage to structural steel, mechanical rough-ins, and interior finishing work across 4 floors before firefighters brought it under control. The direct physical damage was estimated at $4.2 million, but the project schedule was disrupted by approximately 5 months while engineers assessed structural integrity, damaged work was demolished, and replacement materials were procured and installed.

The extended timeline triggered substantial additional costs beyond the physical repair. The development company continued to pay interest on drawn loan amounts during the delay, incurred ongoing insurance premiums for the uncompleted structure, and absorbed consultant fees for revised scheduling and engineering review. Marketing commitments made to prospective purchasers required adjustment, and the delay pushed occupancy of the first units past the date when rental income had been projected to begin offsetting carrying costs. The general contractor submitted claims for extended general conditions and acceleration costs, while several subcontractors asserted that the delay entitled them to additional compensation under their respective contracts.

The development company's insurance broker received notice of the loss and began working with the insurer's adjuster to determine the scope of coverage available under the builders risk policy for both the direct physical damage and the consequential financial losses that continued to accumulate as reconstruction proceeded.

More in this program

Professional Liability and Errors & Omissions Insurance
~50 min · $149
Directors and Officers Liability
~50 min · $149
Cyber Liability Insurance
~30 min · $79

Rate this course

Complete the course to share your rating and feedback.